20 September 2021

𝗣𝗿𝗼𝗴𝗿𝗲𝘀𝘀 𝘂𝗽𝗱𝗮𝘁𝗲:

Thanks to the support of the public, during the Tshechu Holidays, we finished laying the GSB (Granular Sub Base) from the Old Zilukha Roundabout till the Supreme Court, which stretches about 850m. We will now start laying the WMM (Wet Mix Macadam) and the blacktopping will begin from 1 October 2021.

This Four Lane Road Development Project, which only started in May 2020 will come to an end by the last week of October. We are very grateful for everyone’s support so far and we ask for your continued cooperation during the final stages of the project.